Wastewater Pump Installation Guide

Professional installation procedures for safe, reliable pump operation. Comprehensive guidelines for submersible, dry-pit, and specialty pump installations.

Safety Requirements & Precautions

⚠️
DANGER: Wastewater pump installation involves electrical hazards, confined spaces, and hazardous gases. Only qualified personnel should perform installation work. Follow all local codes and safety regulations.

Electrical Safety

  • Verify electrical power is disconnected and locked out
  • Use GFCI protection for all electrical connections
  • Ensure all wiring meets NEC and local electrical codes
  • Test insulation resistance before energizing pump
  • Provide proper grounding for all electrical equipment
  • Use appropriate PPE including insulated gloves and safety glasses

Confined Space Safety

  • Test atmosphere for oxygen, hydrogen sulfide, methane
  • Provide continuous ventilation during work
  • Use appropriate respiratory protection equipment
  • Maintain communication with surface personnel
  • Have rescue equipment and procedures in place
  • Follow permit-required confined space procedures

Lifting & Rigging Safety

  • Calculate total weight including pump, motor, and fluids
  • Inspect all lifting equipment before use
  • Use proper lifting points and rigging hardware
  • Maintain clear area below lifted equipment
  • Follow manufacturer's lifting procedures
  • Use tag lines to control pump during lifting operations

Personal Protective Equipment

  • Hard hat and safety glasses (minimum requirement)
  • Steel-toed safety boots with slip-resistant soles
  • Chemical-resistant gloves for wastewater contact
  • Full-body harness for work in wet wells
  • Gas monitor for continuous atmosphere testing
  • Emergency eyewash and shower facilities nearby

Pre-Installation Requirements

1

Site Preparation & Inspection

Required Tools & Equipment:

  • Measuring tape and level
  • Lifting equipment (crane, hoist, or tripod)
  • Electrical testing equipment
  • Atmospheric monitoring equipment
  • Hand tools and pipe wrenches
  • Sealing compounds and gaskets

Site Inspection Checklist:

  • Verify wet well dimensions match pump requirements
  • Check electrical service capacity and voltage
  • Confirm adequate access for equipment installation
  • Inspect guide rail system alignment and condition
  • Verify discharge piping connections and support
  • Test wet well for structural integrity and leaks
  • Confirm control panel location and wiring routes
2

Equipment Verification

Pump Inspection:

  • Verify pump model and specifications match design
  • Check for shipping damage or missing components
  • Test motor insulation resistance (minimum 10 megohms)
  • Verify rotation direction (for dry-pit pumps)
  • Inspect mechanical seals for damage
  • Check oil levels in seal chambers
  • Verify all fasteners are properly torqued

Documentation Review:

  • Installation drawings and specifications
  • Electrical connection diagrams
  • Operation and maintenance manual
  • Pump performance curves and data sheets
  • Warranty registration information
  • Local permit requirements and inspections

Installation Procedures by Pump Type

Submersible Pump Installation

1

Guide Rail System Installation

Guide Rail Alignment:
  • Install upper guide rail brackets at wet well rim
  • Lower guide rails into wet well using lifting equipment
  • Align rails vertically using plumb bob or laser level
  • Secure bottom rail brackets to wet well floor
  • Verify rail spacing matches pump guide dimensions
  • Test guide system with dummy weight before pump installation
Pump Size (HP) Guide Rail Spacing Minimum Wet Well Diameter Rail Material
1-5 HP 18-24 inches 4 feet 316 Stainless Steel
7.5-25 HP 24-30 inches 5 feet 316 Stainless Steel
30-100 HP 30-36 inches 6 feet 316 Stainless Steel
2

Discharge Connection Installation

Discharge Elbow Assembly:
  • Position discharge elbow at proper elevation for pump connection
  • Install elbow with flexible coupling to allow pump movement
  • Verify elbow orientation aligns with pump discharge
  • Install check valve in accessible location above elbow
  • Provide union or flanged connection for pump removal
  • Support discharge piping to prevent stress on pump
💡
Best Practice: Install a flexible coupling between the pump discharge and rigid piping to accommodate thermal expansion and minor settling.
3

Pump Lowering & Connection

Pump Installation Procedure:
  • Attach lifting cable to pump lifting lugs (never lift by power cable)
  • Guide pump into wet well using tag lines
  • Align pump guides with rail system
  • Lower pump slowly, checking for binding or misalignment
  • Seat pump coupling fully onto discharge connection
  • Verify pump is properly seated and level
  • Connect power cable to junction box with watertight seal
  • Install cable support to prevent strain on connections
Final Connection Verification:
  • Test pump coupling connection for leaks
  • Verify power cable connections are secure and dry
  • Check that pump cannot be lifted without deliberate action
  • Confirm all lifting equipment is removed from wet well
  • Test pump guides allow smooth vertical movement

Dry-Pit Pump Installation

1

Foundation & Mounting

Foundation Requirements:
  • Verify foundation is level and properly cured (minimum 7 days)
  • Check anchor bolt locations against pump baseplate
  • Install pump baseplate with precision leveling
  • Grout baseplate ensuring complete contact with foundation
  • Allow grout to cure before pump installation
  • Verify baseplate is within 0.002" per foot levelness
Pump Mounting:
  • Position pump on baseplate using lifting equipment
  • Align pump with motor coupling (if separate)
  • Install and torque all mounting bolts to specification
  • Check pump and motor alignment with dial indicators
  • Install coupling guard and safety devices
  • Verify pump shaft rotates freely by hand
2

Piping Connections

Suction Piping:
  • Install suction piping with gradual transitions
  • Eliminate high points that could trap air
  • Provide adequate submergence to prevent vortexing
  • Install suction strainer if required
  • Support all piping independently of pump
  • Pressure test suction piping for leaks
Discharge Piping:
  • Install check valve close to pump discharge
  • Provide isolation valve for maintenance
  • Install pressure gauge and sampling port
  • Support piping to prevent stress on pump casing
  • Install expansion joints if required for thermal growth
  • Pressure test discharge system to design pressure

Electrical Installation & Connections

1

Electrical Connections

⚠️
WARNING: All electrical work must be performed by qualified electricians in accordance with National Electrical Code and local regulations.

Power Connection Procedure:

  • Verify supply voltage matches motor nameplate
  • Check phase rotation for three-phase motors
  • Install motor disconnect switch within sight of motor
  • Provide proper overcurrent protection per NEC
  • Install ground fault protection as required
  • Connect equipment grounding conductor
  • Test insulation resistance before energizing

Control Circuit Installation:

  • Install control panel in accessible, dry location
  • Connect level sensors per manufacturer's instructions
  • Wire alarm systems and indicators
  • Program control logic and set points
  • Test all control functions before startup
  • Provide control circuit drawings for future reference
2

Control System Setup

Level Control Configuration:

Control Function Typical Setting Purpose
Pump Start Level 3-5 feet above pump Provide adequate submergence
Pump Stop Level 1-2 feet above pump Prevent dry running
High Level Alarm 6-8 feet above pump Warn of pump failure
Low Level Alarm At pump centerline Indicate low flow conditions

Commissioning & Startup

1

Pre-Startup Inspection

Final System Check:

  • Verify all installation work is complete
  • Check oil levels in gear reducers and seal chambers
  • Confirm all piping is properly supported and connected
  • Test electrical connections and insulation resistance
  • Verify control system operation in manual mode
  • Check that pump rotates freely (dry-pit pumps)
  • Fill wet well to appropriate level for testing
2

Initial Startup

Startup Procedure:

  • Start pump and verify proper rotation direction
  • Check for unusual noise, vibration, or leakage
  • Monitor motor current and compare to nameplate
  • Verify pump is delivering rated flow at design head
  • Test automatic control system operation
  • Check alarm functions and indicators
  • Document all operating parameters

Performance Verification:

  • Measure flow rate using calibrated flow meter
  • Record suction and discharge pressures
  • Calculate pump efficiency and compare to curve
  • Verify NPSH available exceeds required
  • Test emergency stop functions
  • Complete manufacturer's warranty registration

Documentation & Handover

Required Documentation Package:

As-Built Drawings

  • Pump installation details
  • Electrical connection diagrams
  • Piping and instrumentation drawings
  • Control system schematics

Operating Documentation

  • Operation and maintenance manuals
  • Pump performance curves and data
  • Startup test results and settings
  • Recommended spare parts list

Warranty & Support

  • Equipment warranty certificates
  • Manufacturer contact information
  • Service and support procedures
  • Training documentation for operators

Professional Installation Services

Ensure optimal pump performance with professional installation services. Our certified technicians provide complete installation, commissioning, and training for all pump types.